Ives Park Pathway Replacement Segment 1
Construction has been on hold from the previous planned August start up due to the final special events scheduled at the park. The work is planned to begin Monday, September 11 after special events for the summer have concluded. Duration of work is estimated to be 30 days from start, pending unforeseen conditions or inclement weather. As a reminder, the extent of work is to replace the existing asphalt pathway with a new ADA-compliant pathway from the picnic table area to the public restrooms near the central play area.